PMAC Basketball Practice Edition

PMAC Basketball Practice Edition PMAC Basketball Practice Edition

Project Description

A 36,000 sq. ft. addition to the existing PMAC Facility, the addition required removal of the existing concourse ramps to be replaced with Stadia Stairs.

  • Owner: State of Louisiana
  • Project Value: $15,300,000
  • Start Date: July 1, 2008
  • Completion Date: March 1, 2010
  • Project Duration: 1 year, 8 months