Airport Cargo Dock
Project Description
Scope of project included demolition of an existing airplane hangar and construction of a new cargo building comprising 42.000 sf with a 165'-wide clear-span structure, 210' long with 38' eve height. Cargo area included high bay lighting, dry pipe fire protection system, wall mounted louvers and exhaust fans.
- Owner: City of Baton Rouge / EBR Parish
- Architect/Engineer: Go Tech
- Project Value: $2,410,000
- Start Date: Nov. 4, 2004
- Completion Date: May 1, 2005
- Project Duration: 5 months, 3 weeks